on 08-06-2015 4:49 PM
Hello Gurus,
I have one problem connected with capacity planning during planned order creation and production order creation in discrete manufacturing.
If I create planned order with MD11, type LA and conduct capacity check I can see overload (pop up). But at the same time, material, plant etc. during production order creation CO01 I do not have overload. System says all capacities available although I have firmed (fix) planned order on machines.
I have capacity activated in prod. order open and released, both.
Please suggest why is not working in the same way or how propose solution to have it for planned and production ord. the same.
Thanks and Regards
Kat.
Hello,
thank you for this valuable input. Unfortunately Basic Load was done but still not fix. capacity tag in planned order. Same situation now:
1. Planned order overload
2. Production order all capacities available.
Do you know what can be still wrong or different?
Rgds. Kat.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Okay, thank you. Do you maybe know the possibility to adapt capa check in production order custom standard in such way like in planned order?
This is what my key user would like to have. One to one behavior in plan and production.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Katrin
On the SAP Help link previously mentioned we can find the following information:
The logic of the capacity availability check is based on a basic load that consists of dispatched operations and operations with confirmed capacity - as defined in the standard profile. Any other definition could lead to incorrect results in the capacity availability check. You are therefore advised to use only the standard settings.
You may try to change your selection profile to include actual and planned capacity requirements. I have never tested this change but it may work.
Be aware that the SAP Help clearly suggests you to use the standard settings, as the capacity availability check was created considering these specific profile settings.
BR
Caetano
Hello,
thanks for prompt reply. Yes, both are checked. All settings in both transactions are the same.
Regards
Kat.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Capacity availability check of a production order always considers only the basic load on any work center, that means, the confirmed/commited capacity.
Since the capacities have not been confirmed/committed, system shows that there is enough capacity available for the production order. In order to evaluate the basic load, transaction CM07 with overall profile SAPSFC010 may be the best option, since CM01 shows all scheduled capacity requirments.
The definition of the basic load can be found in the SAP online documentation, on the following link:
Determination of Basic Load - Capacity Leveling (PP-CRP-LVL) - SAP Library
You can also review the following notes, which provide more details about the basic load and the availability check:
159337 - Capacity Check: Basic Load
160613 - Capacity check: Capacity availability check
BR
Caetano
Hello Katrin,
Check for SPRO settings in OPU5 for planned order type (LA) - Plant combination and also OPU3 for Plant - Production Order type combination.
Do you have "Generate Capacity requirement" selected in both the cases under detailed scheduling ?
Regards,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.