Dear all,

I have an integration process with PP.

Step 1. COR2 Production order with a component stored on a logistic stored location L001.

Step 2. COIK. Production order picking. To identify the production order for the LP10.

Step 3. LP10 Prepare Production Supply (P) the system creates a transfer requirement. But I can indicate only one production order.

There is a way to do the LP10 for more than one production order?

Cheers,

Marta

replied

define these as a release order part In control cycle and use t-code MF60 to create TR for group of Production order