Hi Expert,

Looking for you help to understand the relation between material avail.date in sales order (ECC) & availability
date in APO.

Please refer attached screen print for details.

Rgds

SDB

Accepted Solutions (1)

Accepted Solutions (1)

babu_kilari4
Active Contributor
0 Kudos

Hello SDB,

Can you post the screenshot of the //RRP3 ATP screen or CO09 screen. I see the discrepancy in the the MBDAT in your screenshot. But, I would like to understand if there are multiple schedule lines in the order ? Or is this the only schedule line ?


Did you try running the /SAPAPO/SDRQCR21 program ? Did it report any inconsistency between R/3 and gATP schedule line dates ?