Dear All,
Its been a while since I actually configured a complete MTO process...
I was just brushing up things and tried to generate a project from Sale order directly.
But I am unable to do so
I have maintained all standard settings I know
item categories, requirement class, MRP groups in Material master, requirement class and order type assignment,
SD MM settings are standard
material to std.network assigned
Project profile is not one root
Coding mask has minimum SO number range
But I am unable to generate the project
I know it is quite a vague explanation but if you guys can help me, it would be very much appreciated
I do have the config document of the last time I implemented MTO but the settings are same now
And I am wondering the reason
Can you let me know step by step what needs to be done
I can verify the same
I shall now mention what I have done step by step :
Master data:
WBS and network template
material assignement to network
material master MRP and sales view
Config:
SD order type remains standard
requirement class
strategy group to requirement class
item category group
item category assignment
strategy group 85 and MRP group PD
planning group 21
requirement types
Regards
Vittal
Hi Vittal,
Can you check the following:
1. Strategy group maintained for the material being used in SO.
2. In Requirement Class Settings it is Q
3. In Requirement Class check for assembly type . I think it should be 2.
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well there was a processing error in the Background due to insufficient storage space PXA
Honestly i didnt know what this was until our developer helped clear the problem
This usually Comes when the allocated space is less for runnning Transactions, this is what i got to know
But nevertheless Project is being created now with same data and same method.
Thanks for all your inputs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vittal,
regarding Assembly Process below are the settings required:
MM:
Material master should have Gen category group as NORM
MRP type-PD
Strategy Group-85
should be connected via CN08 (Material and std WBS & Std Network)
Standard Project should have SD/PS Assignment tick
Now requirement classes:
default 212 is used where Special stock is E and account assignment is D as defaults.
strategy group as 85 where main strategy should be 85
strategy groups should be assigned with requirement type and requirement class as KMPN and 212
also check plant and mrp group assignment with strategy if any.
then if you use material in sales order than a project structure will be created using standard wbs and networks.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vittal VR,
After necessary configuration from SD,PP
Pre-requisites from PS for Assembly processing:
1) Standard WBS element(create it)
2) Standard Network(create it)
3) Activities/operations must be linked to Standard WBS elements(logical connectivity of Std n/w and WBS elements)
4) As total process is being triggered from SD we must maintain Sales views in Material master(Also,in MRP-1 view use MRP type-ND instead of PD)
5) We must allocate the material to Standard network using CN08 transaction
In OVZG transaction, check the req class and type
Create sales order using PS1 order type,
In the account assignment tab you will get WBS element automatically and upon saving notedown the project number
Best regards,
Sriramm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.