Dear Experts
Currently my budget Tolrenece Limit is 100%.
Now, i changed the budget tolarence limit to 110% and saved.
I have done the availability control activiation and deactivation and reconstructed the availability control.
Released Budget is for Rs.2000.
Now i am creating a Purchase Requisition against WBS element and the Valuation Price is allowing upto Rs.1900 (95%).
If i am giving more than Rs.1900, then it is throughing an error message like "Budget Exhausted".
I want to use the budget upto Rs.2200 which is maintaind in the tolarenece limit.
How can i achive this?
Please suggest.
Regards
Mohammad.
Hi Mohammad Shaik,
Check the following:
1. any assigned values for the WBS where you are planning to raise a PR?
2. Is the WBS for which PR is being raised has person responsible data maintained?
Can you share the error screen shot full text.. and Also setting for your budget profile in use and tolerance limits..
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohammed,
Please maintain the person responsible at the WBS and you will not get this error. As in Tolerance Limit you have choosen warning message + email for 95% usage. This setting requires a person responsible to be maintained, which is causing this issue..
if you see your second warning message it says agent couldn't be determined to send the message..
Please maintain the Person Responsible at the WBS and you should be good.. If you still face issue let me know..
Regards
Sammar
HI,
Can you share the screen shot of the changes that you have made in configuration and also check the available budget in the wbs.
Thanks
Soni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.