on 08-04-2015 9:19 AM
Hello,
Let me try and explain my requirements....
We have configured ZMCR (RFC) and 2 Change Documents ZMMJ (Std Change) and ZMHF (Urgent Change) to support the change control process for my client.
My client now has a requirement that when the Change Document is set to status 'Successfully Tested' they require the transport to be automatically imported to the PRD system bypassing the status 'Authorised for Production' and once imported to PRD the Change Document is set to 'Imported to Production'
Can this be achieved through the use of ZMHF (Urgent Changes) and if so can you please advise on how this could be achieved? Do we need to configure a new Change Document type to support this process?
We have configured the Preliminary Import user statuses in ChaRM to support this process in the ZMHF (Urgent Change) change document type.
Regards,
Gary B
Rishav/Prakhar,
Many thanks for the suggestions this is exactly what we are looking for!!
I will try this in the Development system and update this thread with the results (hopefully positive!!)
Thread closed
Gary B
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Gary,
You can check below links for scheduling imports jobs
Importing Transport Requests: Options - Project and Transport Administration - SAP Library
hope this helps.
Thanks
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Any progress ?
Regards
Rishav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gary
Urgent change will move to production system irrespective of the maintenance cycle as they follow its own maintenance cycle. so you should be very carefull here while doing this. Also there are two strategies for the task list SAP 0 and SAP1 with which you can remove the transport once imported into production in order to avoid the further movement. You will assign this while you are creating maintenance cycle/task list of project.
There is one more check you can implement or you can try, status dependent import and it will import the changes only when the status is succesfully tested.
But I will recommend if you are doing any type of customizations like this it should be thouroughly tested in the test system first.
Please find below links for same and see if you can utilize that
http://help.sap.com/saphelp_sm71_sp05/helpdata/en/61/e7f3c065a54a7db584e22936d8e97e/content.htm
Please post me if you had further queries.
Regards
Rishav
Hi,
Can you check the assigned actoins for the same and yes then you can change the status automitically to "Imported into production" via below report.
SE38-> CRM_SOCM_SERVICE_REPORT
Schedule it as background job with the appropriate variant.
Assign action IMPORT_PROD to the E0004 status and try if it worked for you.
SPRO->Charm->Change request mangement framework->Make settings for transaction types.
Regards
Rishav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.