shift sequence +cm25

we defined shift sequence (op4a) as 5 days+2 shifts. 5 days will have 3 shifts and 2 shifts on saturday. same is assigned in resource and checking the cm25 time lines and showing saturday as holiday. tried by making active version in resource, still could not get 2 shifts on saturday. also tried with cm25- settings- calender- show. this also not resulted in any chnage in the cm25 display. could any one tell me where we should make the change so that cm25 will show as per shift sequence.

replied

Hello,

Can you check your factory calendar and confirm if Saturday is defined as a working day ?

Check using transaction SCAL the factory calendar maintained against the plant.

In the factory calendar, check that is Saturday defined as a work day.

If not change it make Saturday a work day, and check CM25.

Best Regards,

Ameya B.