on 08-03-2015 7:57 AM
Dear Exparts
We have configure the sub contract process. But we are facing one issue regarding the costing issue of Sub contract material.
Sub contract material is a Finished goods. So that price indicator will be S as per our understanding.
But this material has no BOM because this material is not produce in our plant.
We also add the sub contract charge (expenses GL) in the cost component structure.
Basic information of Sub Contract
Configuration of Sub Contract Process
Now what will be correct price indicator of Sub contract Material and how we will solve the below issue.
Sub contract charge (BDT 600) should be add with the Raw Material Cost (BDT 10).
Regards
Tarek
Hi Tarek,
In this case your FG should have the price control indicator 'V'-MVP. Then only your raw material cost and subcontract charge will reflect to your FG.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.