cancel
Showing results for 
Search instead for 
Did you mean: 

What key figure should be used to load the demand planning back to ECC?

Former Member
0 Kudos

Hello,

Once the S&OP plan is approved and constrained - what right key figure that should be loaded back to execution SAP/ECC? Right signal to the planners to execute the plan.

Thanks, Renata

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks Alecssandra.

In our case production receipt is net out of the inventory on hand (we bring from ECC and net out the demand). If we use product receipts MRP will net out again - giving the wrong signal to the planners.

Do you happen to have any other examples?

Thanks

Alecsandra
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Renata,

One example I have is sending the Production Receipts to ECC as PIR (Planned Independent Requirements). PIRs and dependent requirements are then used by MRP to create Planned Orders.

Regards

Alecsandra