Hello,

           The capacity planning period ( start and end) is derived from the Item's forecast start and forecast finish. Is there a way to modify the range ( ex. the range should be based on planned start and planned finish) based on other dates?

thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

judith_gabriel
Contributor
0 Kudos

Dear Anantharam,

when the field "forecast start" is filled in item on tab "general information" this date is used as "period from" value in the financial/capacity planning.

When the field "planned start" is maintained - then this date is used for "period start".

When both fields are filled the "forecast start" is used for the "period from" determination.

This occurs in:

/RPM/FIN_CAP_PLANNING            

VI_PLANNING_ALV

ALV_FCODE_SHOW_ALL_PERIODS    

Best regards,