on 07-31-2015 10:28 PM
Hello,
The capacity planning period ( start and end) is derived from the Item's forecast start and forecast finish. Is there a way to modify the range ( ex. the range should be based on planned start and planned finish) based on other dates?
thanks.
Dear Anantharam,
when the field "forecast start" is filled in item on tab "general information" this date is used as "period from" value in the financial/capacity planning.
When the field "planned start" is maintained - then this date is used for "period start".
When both fields are filled the "forecast start" is used for the "period from" determination.
This occurs in:
/RPM/FIN_CAP_PLANNING
VI_PLANNING_ALV
ALV_FCODE_SHOW_ALL_PERIODS
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
6 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.