Not able to distribute budget using IM52

Hi All,

Greetings for the day !!

I have created one scenario in Investment management. Scenario is like.

1. I have created Program and program 1st position "1000".

2. Under 1000 position I have created 5 different level and under each level there is more 5 different level.

3. I have released whole structure.

4. I have created One Appropriation request under multiple position (60% and 40% to two positions)

5. I have done cost planning.

6. My Appropriation is Approved and I have created Measure as project from ima11 only. Then I have released my appropriation request.

7. Further to this I have rolled up all planned cost.

8. I have assigned original Budget to Positions as per cost panning.

till this I haven't got any error and process seems to be correct but now when I am trying to distribute budget to my project. System is generating an error No measures found Message no. AP083.


As per my understanding when we assign Appropriation request to multiple positions we can not distribute the budget.

Now my Question how can i distribute budget to my project from IM?