Manufacturing Variance Account In Cost Component Structure

Hi,

May i know if we need to include the manufacturing variance account in cost component structures? If yes should we label it as "Manufacturing Variance"? Please advise.

Former Member replied

Hi Sanjay

You need not to include variance in CCS...

1. In standard cost there is no question of variance..

2. In actual cost if ML/Actual costing is active during ML run all differences in various levels are absorbed in product level...so CCS does not need variance to assign

Kamal