Transfer recipes from one system (productive) to another system.

Former Member
0 Kudos

Hi all! I need to copy the master recipe (PP-PI) of the productive system to the test. I know that can be copied using IDOC classes, characteristics, material master records, and other basic data. But I can not find how to copy the master recipe. Program / SAPMP / RBDSERU not suitable, because there only copying Routings (type N), there is no way to copy the master recipe (type 2). Copying systems are not suitable for various reasons. It is only necessary to copy the recipe. Please help me.

Accepted Solutions (1)

Accepted Solutions (1)

ameya_beri
Active Contributor
0 Kudos

Dear Ivan,

Have you checked standard transactions POIM and POIT ?

Best Regards,

Ameya B.

Former Member
0 Kudos

Hi Ameya! Earlier I did not know about these transactions. It seems that this is what I need. Thanks for the help!