GR posted for zero quantity

Hi Guru's

User have posted GR for zero quantity and done IR before GR ( GR based IV was not active).

And now user is unable to reverse GR because GR quantity is zero.

I tried replicating in quality and its not possible to post GR for zero quantity and when raised question then user is unable to update how they were able to do GR for zero quantity.

I have suggested them to cancel material document in MBST transaction, but got update from user that "line item doesn't exist" and now i have asked user to save in MBST and awaiting their reply.

Please advise if this will resolve this reversal issue or there is any other procedure to fix this issue?

Regards

Irfan A B