on 07-28-2015 4:18 PM
Hello Guru's,
When calculating my start date for a production Order, if my Goods Issue date falls on a holiday or on a weekend do the SNP heuristics push my start date backwards or does it move my demand date forward? Below is an example:
Demand Date: Aug 04 2015
Production Time : 2 days ( Calendar 5 days a week)
GI Time : 1 day ( Calendar 5 days a week)
GR Time : 1 Day ( Calendar used 7 days a week)
In Above example:
I need product ready by Tuesday.
GR Day : Monday
GI Day : Sunday . since this is a holiday do heuristic push by GI date to Friday or Monday?
Thank You in advance
Srikanth
Hi,
Depends of your capacity, the heuristic will assure that by Tuesday the PO will be ready. The heuristic will do a background scheduling!
Thanks,
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check this link: https://www.consolut.com/en/s/sap-ides-access/d/s/doc/H-$SAPAPO$SVTTY
Thanks, Marius