Goods Issue date on Holiday or Weekend

Former Member
0 Kudos

Hello Guru's,

When calculating my start date for a production Order, if my Goods Issue date falls on a holiday or on a weekend do the SNP heuristics push my start date backwards or does it move my demand date forward? Below is an example:

Demand Date: Aug 04 2015

Production Time : 2 days ( Calendar 5 days a week)

GI Time : 1 day ( Calendar 5 days a week)

GR Time : 1 Day  ( Calendar used 7 days a week)

In Above example:

I need product ready by Tuesday.

GR Day : Monday

GI Day : Sunday .  since this is a holiday do heuristic push by GI date to Friday or Monday?

Thank You in advance

Srikanth

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Depends of your capacity, the heuristic will assure that by Tuesday the PO will be ready. The heuristic will do a background scheduling!

Thanks,

Regards, Marius

Former Member
0 Kudos

Thank You Marius.

If I have enough capacity does heuristic move my GI date to Friday?

Regards,

Srikanth

Former Member
0 Kudos

Yes. But you have to also check if you are using safety days supply in the product master!

Thanks, Marius 

Former Member
0 Kudos

Thank you..

Could you please explain me how safety days is going to effect?

Thank you

Srikanth

Former Member
Former Member
0 Kudos

I couldn't understand how this effects my GI date to move forward?

Could you please explain how it effects my calendar ?

Thank You

Srikanth