Dear PM Guru,

I have a query about Work Center, is it Maintenance Planning Plant dependent or Maintenance Plant Dependent.          

Payal Gupta

Former Member
Former Member replied

Hi Payal,

Let me throw some more light on this,

In case of Centralised Planning -

1.If same Maintenance Team is responsible to perform maintenance activities at all the maintenance plants then Work Center used in orders belongs to Planning Plant

2.If separate Maintenance Teams are responsible to perform maintenance activities at there respective maintenance plants then Work Center used in orders belongs to Maintenance Plant

In case of De-Centralized Planning - Work Center will work as Plant dependent because in this case both Planning Plant & Maintenance Plant are same.

Hope this will help you to understand.

Thanks.

Amol