on 07-27-2015 2:57 AM
In IBP for S&OP, at the customer-product location, "constrained Demand Plan Qty" is not calculated even though "Consensus Demand Plan Qty" is populated.
Please let me know which master data to check so that I can figure out why "Constrained Demand Plan Qty" key figure is empty
It is working fine for other customer-product location and I have checked master data and it looks fine.
Thanks,
Tauseef
Hi Tauseef,
Did you check if the specific combination of cust, prod and loc is maintained in the Customer Source master data?
Regards,
Alecsandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tauseef,
Please make sure your supply chain is complete and all relevant sourcing quota is maintained for this particular customer-product combination(customer source, location source and production source).
If still constrained demand is not generated after running supply plan then please post all the three master data screenshots mentioned above.
Thanks,
Rohit
Hi Alecsandra,
I am facing the same problem of "constrained demand plan" key figure is not populated when I run the heuristics. I have already checked customer, location and production source master data.
I have sent you email with screenshots. Please let me know how to troubleshoot this issue.
Thanks,
Tauseef