Release to SNP issue

Hi experts,

I have an issue in releasing the DP to SNP , Heres the situation:

we have a weekly release to SNP.

I make the changes on wednesday to a manual input KF ( For Eg 10) , then on wednesday the forecast is calculated. Then again change the value to 20 on thursday , saturday is the release to SNP. It should have released 20.

When the release happend, it has released only 10 , but not 20. What could be the reason for this?

Regards

Sam.

Former Member