Pm order business complete doubt

Hi all,

Can any one let me know who will close the pm order either by FICO department or by pm department.

replied

TECO i.e. Technical completion is done by Maintenance team while business completion is done by the Finance team after doing the settlement of the work orders.

Hope this helps!

Thanks,

Tajinder