Hello all ,

Please guide me how to understand CM28  report.

Thanks

Nishu

Accepted Solutions (0)

Answers (1)

Answers (1)

sammar81
Employee
Employee
0 Kudos

Hi Nishu,

this report is used to evaluate the capacity of your work centers. Let's say you have Work Center X which is used in 10 different projects.. And you need to check on the used and available capacity on the work center you can use this report...

for more details on the Capacity planning and leveling i would suggest you to read through the sap help on capacity planning in PS..

Capacity Requirements in Projects - Capacity Planning in the Project System - SAP Library

Former Member
0 Kudos

thanks Sammer...