PIR HISTORY QUANTITY FLUCTUATIONS

Dear PP Gurus,

Material history in md63 showing quantity difference in Old & Planned Quantity

P Reqmts dt.   Planned qty       Old qty   Chge date

M 07.2015           8,260             0     26.04.2015
M 07.2015           7,000         8,260     18.06.2015
M 07.2015           3,000         7,000     04.07.2015
M 07.2015           2,900         3,000     11.07.2015
M 07.2015           2,000         1,300   

19.07.2015

As per above there is difference showing.... 

Current Quantity in PIR: 1600,  Withdrawal Quantity= 400.......... This is Consumed from 2000

But I want to know  Why old quantity = 2900 not showing...... but system shows 1300 Why??

Reqmts typ: BSF  Strategy=11  Consumption mode=2  Forward & Bkd Consumption=30  Availability Check=01

Please Help..!!

Regards,

Madhukar Poul 