on 07-23-2015 11:22 AM
Dear PP Gurus,
Material history in md63 showing quantity difference in Old & Planned Quantity
P Reqmts dt. | Planned qty | Old qty Chge date |
M 07.2015 | 8,260 | 0 | 26.04.2015 |
M 07.2015 | 7,000 | 8,260 | 18.06.2015 |
M 07.2015 | 3,000 | 7,000 | 04.07.2015 |
M 07.2015 | 2,900 | 3,000 | 11.07.2015 |
M 07.2015 | 2,000 | 1,300 | 19.07.2015 |
As per above there is difference showing....
Current Quantity in PIR: 1600, Withdrawal Quantity= 400.......... This is Consumed from 2000
But I want to know Why old quantity = 2900 not showing...... but system shows 1300 Why??
Reqmts typ: BSF Strategy=11 Consumption mode=2 Forward & Bkd Consumption=30 Availability Check=01
Please Help..!!
Regards,
Madhukar Poul
Hello
Not all the changes are logged by default. Go to transaction OMP4 and make sure that both flags are checked for your requirement class.
See the note below for details:
1875219 - Change documents of planned independent requirements
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.