on 07-22-2015 3:50 PM
Hi
We have scenario where planning and release generation for Scheduling Agreement is happening in SNP and then we are releasing this schedule line using transaction /SAPAPO/PWBSCH1. This creates new release schedule lines in ECC SA.
Now we want to transmit this new release to vendor via EDI message. So question is how to set up automatic trigger of output message from ECC to vendor in this scenario? There are settings available on APO side to trigger output for vendor but we want to send output from SAP and want to confirm if this is possible in standard SAP.
Additional info:
Doc Type: LP
External planning : 1 (Planning and Release Generation in APO)
Output Message: LPET
Regards
Hi Sandhya
Check below links which explain the same:
Prerequisites for the APO Scheduling Agreement - Supply Network Planning Run - SAP Library
Scheduling agreement release documentation - ERP SCM - SCN Wiki
Messages for Scheduling Agreement Releases - Purchasing (MM-PUR) - SAP Library
Output determination Scheduling Agreements | SCN
Scheduling Agreement --- IDOC Setup | SCN
Meanwhile you can cross check more in Google/SCN itself. If already answered follow .
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.