Dear Gurus,
After I run the SNP heuristics in APO, I got some planned orders in planning book. But when I check MD04 in ECC, I found real planned orders are generated (There is no such order before I run the SNP heuristics), And from the action date/time and the action APCR, I know ther are newly generated.
When I run CCR afterwards, I can see those planned orders shown as difference in content, but no matter I wanted to push those to APO from ECC or the opposite way, nothing happened. (CQ are cleared before CCR.)
Really appeciated for your answer. I'll give points.
BR,
Yang
Hello Yang,
ECC does not have categories to differentiate SNP and PPDS order Type . Both the planned orders are treated as same order type in ECC.
Regards,
Nick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yang
Check KBA
2061534 - Who and what created this PPDS planned order?
1891961 - Trouble shooting guide: Planned orders are not published to ECC after SNP planning
With 1891961 you will understand what has been done which is shifting the same. Lets us know if it helped.
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yang,
Go through the below link
I hope this answers your above question
Regards
Rahul