I have following issue in our company. The PM department have an daily worktime from 7 am to 4,30 pm. This time is from Monday to Thuesday, on Friday, they work from 7 am to 12,30 pm.

So how could i set my capacity times? The problem is we also do shift work, every week another guy from the department. So i cant set up an shift model for the Monday to Friday issue.

Anyone a hint for me?

Best Regards

Florian

Accepted Solutions (1)

Accepted Solutions (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Florian,

Let me understand, what is stopping you from using the "Intervals and Shifts" functionality? Do you use HR personnel number integration?

You could, under Work Centre > Capacity Header > Intervals and Shifts:

Define a Shift Definition and Shift Sequence for your Mon-Thu workdays, Fridays and weekends, then assign that to your capacity. You can also define the number of Capacities. So your Interval definition could look something like this:

Answers (1)

Answers (1)

0 Kudos

Hi Florian,

If your work hours is 7 to 4:30 from Mon to Thur = 9h30min*4= 38 hrs.
and on Friday= 5hrs 30 min, on a regular factory calendar for a week you will  have 38+5,30= 43hrs 30 min.You can split the hours equally among the five days. 8hrs 42min a day like 7am to 3:42pm. Likely  you can set up the capacity of work center accordingly.