cancel
Showing results for 
Search instead for 
Did you mean: 

How transport duration related with purchase requisition?

former_member332160
Participant
0 Kudos

Hi Expert,

I wants to know how the transport duration (from transportation lane) is related with purchase requisition in /sapapo/rrp3 ?

How planned delivery time is calculated in purchase requisition?

Please share the info on the same.

Many Thanks!!

Accepted Solutions (0)

Answers (2)

Answers (2)

RahulHanda
Active Contributor
0 Kudos

Hi Jeet

Go through the below thread (also the notes mentioned in the same) and link.

Planned Delivery Time and Requirement Date in ECC | SCN

Determination of Dates/Times - Integration of Transaction Data - SAP Library

Regards

Rahul

former_member332160
Participant
0 Kudos

Hi Rahul,

Thanks for reply!

one more question there is gap of one day between ECC and APO purchase requisition.

In APO its showing 24 days but in ECC its 25 days are coming.

former_member332160
Participant
0 Kudos

HI Rahul,

When the Purchase requisition comes in ECC from APO the planned delivery time geting incease by one day.

For example- IN APO start date of PR is 15.08.2015

but in ECC in  PR its 14.08.2014

can you provide advise on this.

Former Member
0 Kudos

are the timezone in both system same?

also are the calenders are same?

Pravin

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Today is  7/21/2015. The planned delivery time is 10 days, On this basis, the earliest delivery date calculated is Today date  plus 10 day PDT = 31/07/2015. Therefore, if an order is placed today, the vendor can deliver on 31/7/2015 at the earliest. The vendor needs two days for transportation and one day for goods issue processing. As both the transportation time and the goods issue processing time are contained in the delivery time, they are subtracted from the earliest possible delivery date to calculate the earliest possible start time 31/072015 minus two days, minus one day = 29/07/2015 as the start of validity. In order that the vendor can deliver in time, goods issue can only start on 29/07/2015 at the earliest (= start date of the purchase requisition).

In product view RRP3 view if you click on the Preq and go into details, in the activities details you can see the start of activity and the end of activity,the difference is nothing but Planned deliver time Transportation duration.

Please refer consulting note

   379006 - Transport duration and planned delivery time in APO and R/3.

Determination of Dates/Times - Integration of Transaction Data - SAP Library

Best Regards,

R.Brahmankar

former_member323340
Participant
0 Kudos

Hi Brahmankar

I have a issue, where for some purchase requisition, the transportation activity comes up when we see the details of the activities within the PR in RRP3, however for some PRs the transportation activity is missing here.

Accordingly the start date of the PR is also varying. Ideally we expect that the transportation activity should be coming for all the PRs.

What could be the issue.

Thanks in advance.