Hi All,
We are having a scenario where CTP creates planned order against the MTO sales order. PPDS will then reschedule all orders based on certain production planning requirements.
Then BOP or executing VA02 is supposed to provide new requirement date based on changed planned order date by PPDS. When we execute VA02 we see that existing planned order /process order is ignored by CTP and it triggeres new planned order creation.
We have all relevant ATP categories included in scope of check. Also there is no "receipt recreate" checkbox selected in check instructions.
Kindly suggest what might be triggering this incorrect behavior.
We are on EHP3 for SCM 7.0.
Best regards,
Vaibhav
Hello,
The sales order item that is called for the CTP check exists within an individual customer segment
the main output of the planned order whose components are to be checked also exist within the same individual customer segment. In that case system will generate the planned order within an individual customer segment (make-to-stock segment)
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This could be happening for a couple of reasons -
Your expectations are justified. The date changes to the old planned order should be picked by the SO on VA02/re-ATP. Assuming the old planned order gets set with a OUTPUT FIRMED check box.