BADI Does not exist error 0RPM_MSP_BADI_1

hi All,

I've followed the steps as in below PPM Config guide and activated the services mentioned. For purpose of 'Settings for Microsoft Project Integration' as described in the Config guide, I've checked SE18 for BADI: 0RPM_MSP_BADI_1 and I am getting an Error: BADI Does not exist

Ref - Config guide: ConfigContPPM60SP03 Pg. 183

Pl let me know on how to continue to get this BADI implemented in system.

Text from Config guide - Pg. 183: If you want to map project structure elements from Microsoft Project to Project Management Project structure elements, you must implement the BAdI: Change Project Plan Data in Project Management and Microsoft Project (0RPM_MSP_BADI_1), which is found the SAP Customizing Implementation Guide.

-Thanks

Helpful Answer

by