By accident too many hours of a resource were issued to a production order, causing an unjust spike in WIP and incorrect production order costing reports.
For normal stock items I could probably fix this by:
Is there any way in SAP to correct this issue?
(Other than creating an offsetting manual journal entry. That would only fix it for financial reporting, the subadministration production costing reports would still show the wrong values.)