on 07-15-2015 3:17 PM
Is there any way to see what are the planned orders or
products deallocated may be in the Alet monitor or any other place
other than Detailed scheduling planning board seeing in different colour
of deallocated planned order
Please suguest
Hi vijaya
You can check Dealloacted orders in DS Board by double clicking on order where you can also change status
Also you can check in product view by double clicking on order you can know status whether it is in scheduling or deallocated status But you can not change here
Hope it is clear
Regards
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The CDPS_REPT report will show you such Orders. Look for the column Fully Scheduled - the box should be unchecked.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi vijaya
You can check in /sapapo/cdps_rept report has suggested by Andy There is column Fully schedule
If it does not have tick mark then it indicates that it is in deallocated status .just take dump into excel and apply filter to report check entries which are in fully schedule and compare with excel . you will get Deallocated orders
Hope it is resolve
Regards
Virender
Hi vijaya
1) First you take dump of CDPS_REPT in excel
2) Apply filter to column Fully schedule where you will not get deallocated orders you will get order which are schedule .same take dump in excel
3) Just compare excel of first step and second step you will get deallocated orders
Or else develop custom report by considering your Abaper
If it is clear close the thread
regards
Virender