on 07-15-2015 11:17 AM
Hi,
You have not yet settled the shipment cost document.
In the shipment cost document, go to the Reference objects tab and you should do the account settlement to the relevant shipment cost objects (sales order, delivery etc) If you do the settlement, then a service entry sheet will be generated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear PB,
Have you mainatin the no. range for servoce entry sheet, please check the same. It might be due to this.
Thanks.
SS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.