RPT issue

former_member205751
Participant
0 Kudos

hello experts

As part of UAT I need to execute the below test in front of all users,

-Reschedule partial order-test interrupt and downtime –

In the above RPT screen I need to execute this.

Process steps to my knowledge :

  1. I need to create a process order first in ECC ( understood)
  2. Partially confirm it ( can do it)
  3. CIF it to RRP3 ( can do it)
  4. Look at the date to which the order belongs ( can do it)
  5. Alter the date and assign it to an unloaded resource ( how to do it ?)
  6. Why is that down time coming into picture? ( perplexed !!! )

Experts can you please help with any document in SAP that explains this /else i invite you to  come to my rescue .

thanks

ohio

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rahul,

Just right click in the pl.order line and you will be able to change the source and reschedule. For down time check at resource level, tab Downtime!

Thanks,

Regards, Marius