on 07-11-2015 8:28 AM
Hello SAP Experts,
Is there any standard report available which gives the details of work center, cost center and period wise activity rate maintained in KP26 ?
Best Regards,
Ameya B.
Ameya,
All details won't be available in one standard report you should consider developing a custom report or query.
Check tables CRCO for Work center to Cost center assignment, and CRHD for WC details.
In Standard reports CR06 and S_ALR_87013617 are some what useful in finding WC,Cost center and Activity type analysis.
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
You can try report CR06, here we get Cost center/Work center/Activity but we don`t get the cost.
To get the cost in single report along withe these parameters you need to develop some program or query.
Regards,
Pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.