Hi all
I am qurius about budgetting on WBS elements. I tried to google around without any answers.
Do you know if it is possibe to create phasing/periodisaiton on WBS elements split on month and not only on whole years?
Thank you in advance.
Best
Lasse
Hej Lasse,
You can simulate monthly budgets with budget releases, provided that availability control is on released amount. That can be part of month-end closing process.
Alternatively you can do budget supplements on a monthly basis. All options are around the system process, not necessarily around "out of the box" functionality.
Mvh,
Paulo