SAP ECC - WBS budgeting

Former Member
0 Kudos

Hi all

I am qurius about budgetting on WBS elements. I tried to google around without any answers.

Do you know if it is possibe to create phasing/periodisaiton on WBS elements split on month and not only on whole years?

Thank you in advance.

Best

Lasse

Accepted Solutions (0)

Answers (1)

Answers (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

Hej Lasse,

You can simulate monthly budgets with budget releases, provided that availability control is on released amount.  That can be part of month-end closing process.

Alternatively you can do budget supplements on a monthly basis.  All options are around the system process, not necessarily around "out of the box" functionality.

Mvh,

Paulo