sampling with DMR

Hello,

History of my question is available to below thread but somehow I marked it to "answered" per previous question I'm posting here second issue regarding sampling.

DMR update to an excising inspection plan

After adding DMR to an inspection plan I found one strange thing regarding sampling. As I said earlier we are not using DMR and we have just one sampling procedure which is fixed size - 1 KG. Even there is no use SDP in our system. So when system creates an inspection lot system won't assign any sample to the lot, but business go in QPR6 and create sample manually to do result recording.

Now after assigning DMR what I found is system auto creates two sample for the lot. One as Pooled sample while 2nd as Primary. I'm not understanding why does system do like that? I do not want system to create two samples at the lot creation.

Reply appreciated.