Hi All,

Split valuation is activated so at the time of Goods issue multiple valuation type can be used but while calculating std. cost only 1 valuation class is assign so system is posting variance under Resource usage variance category.

While calculating std cost of Fg the raw material data will be picked depending on valuation class assigned in accounting view 1 of rm and split valuation is activated so at the time of Goods issue it`s not necessary that the valuation type for raw material to be same as what we have assigned while calculating std cost.

For eg:

While calculating Std cost:

Rm 1(Accounting view 1 Valuation class is Valuation class A)

Rm 2 (Accounting view 1 Valuation class is Valuation class B)

Now at the time of goods issue :

1. If I give same valuation type as valuation class used while calculating std cost the variance will be post under Input price variance.

2. If I change valuation type as Rm 1(valuation type C) and Rm 2(Valuation type A) then system will post the variance under Resource usage variance.

Any suggestions that how can I resolve it.

Regards

Nitu

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member216878
Participant
0 Kudos

Dear All,

Any suggestion!!!!

Regards

Nitu