on 07-09-2015 11:34 AM
Hi, Experts!
I have some problems with integration GRC-ERP. I create connector, script for SAP Table in spro transaction for KRIs, then Create KRI Implementation,
In the Connector Type field, I select a connector type:
At the end I used this KRI Implementation in Risk, but I can't get the values. Look at the screenshort below
Hello.
To get value of KRI by report GRRM_KRI_RUNTIME you need to specify current date (or date of planning execution of the report) in field "Next Execution Date".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Gulzhan,
This might be issue with time frames
check the SAP note
1802252 - GRC RM 10.0 KRI Data time frame is not working
Regards
Baithi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Assuming your setup is correct, have you ran the job using program GRRM_KRI_RUNTIME ??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.