Dear Experts,
Our Customer wants to extract an Excel FIle from PPM Project and he requires to have both Actual Finish Date and Forecast Finish Date.
I can see a list of fields available in Table View for the Project, but there's not the Forecast Date.
How can we add it to the view?
We're using Portfolio and Project Management 5.0
Thank you
Laura
Thank you Judith,
as soon as we can test your solution, I'll mark your question as Correct Answer.
Regards.
Laura
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Laura,
the relevant structures are DPR_TS_UI_TABLE_DATA and DPR_TS_UI_TABLE_DATA_EXT.
The "Forecast"-date-fields are not available in structure DPR_TS_UI_TABLE_DATA_EXT and
so they are not included in the export.
In class CL_DPR_UI_LOG_TABLE with methods GET_AS_SPREADSHEET_TEXT and
EXPORT_TO_SPREADSHEET the structures are filled and exported.
(With BAdI DPR_EXPORT_TO_EXCEL the values of the available structure can be changed.)
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.