Hello,

is there a Job which has to run that I could add requests or tasks? 

When open "my requests" there is an error which says "No data availible"

Best regards,

Laurin

Accepted Solutions (1)

Accepted Solutions (1)

p1024029
Participant
0 Kudos

Hello Laurin,

Check the section 5.3 Setting Up Service Connection for Task Management in http://help.sap.com/saphelp_hana_opint/SAP_OPInt_Installation_Upgrade.pdf.

It should work after setting up the connection.

Cheers,

NB

Former Member
0 Kudos

Isn't it 6.4?

p1024029
Participant
0 Kudos

Sorry,


yes 6.4.

it was 5.3 in my old downloaded version.

NB

Archana
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Laurin,

Yes that is correct. Accessing tasks requires additional authorization that is mentioned in that section 6.4

But please make a note that the guides you are referring is for OpInt 1.0 SPS09 and you have OPInt 1.0 SPS09 installed in your system, together with HANA REV96/97.

In OpInt 1.0 SPS09, we have introduced Administration Cockpit that is health check for configurations requirement of OPInt. This gives you provision to setup the required configuration in just one-click. The one you are finding is the first option in this cockpit.

Find more information in Section 5 : Working with the Administration Cockpit in Installation and Upgrade Guide http://help.sap.com/saphelp_hana_opint/SAP_OPInt_Installation_Upgrade.pdf

Regards,

Archana

Archana
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Laurin,

I would appreciate if you could let me know whether you found the answers helpful by selecting Helpful Answer or Answered. 