GRC AC 10.1 SP09 - Access Request Validity Dates for Existing Roles

binicholson
Explorer
0 Kudos

When changing user access for existing role assignments the valid from date is changed to the current date.  In this process we have users that generally get assigned some temporaty access and need to extend the validity period without changing the existing valid from date.  The same issue arrises in the termination process where we deactivate the user and delimit the existing role assignments, the valid from date always changes to the current date.  Does anyone know where we can control this behaviour and retain the original date for existing assignments?

Regards Bill

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member197694
Active Contributor
0 Kudos

Hello Bill,

Please check and apply the below note for correction.

2120452 - Validity Date of Existing assignment is not coming correctly



Regards