Hello Pratap,
If you change project profile, new project will have one network for project but I think you will not be able to change already created project. They will remain with multiple network under WBS element.
Check in Sandbox before trying in development.
Deepak M Pitale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepak and Maria,
Thanks for your prompt replies. Deepak, as you guessed correctly I knew that I won't be able to change the project profile settings once the project is created. But what I didn't realize is that actually only 2 of those settings are not changeable: 1. 'Network asst' under 'Planning dates' and 2. 'Project stock'. So I wonder if there is any way around this. I'm guessing that settings like budget profile, results analysis key, etc. also get locked once budget, results analysis, etc. are applied to the project.
Thanks again,
Pratap
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As said by Deepak, change the network assistant to '1', this will create network only at project definition level, which means one network for a project.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Pratap,
Check project profile tab Plg board/dates under network, if network assistant is '2' for WBS element then it will create network under each WBS element.
Hope this can answer your question.
Deepak M Pitale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.