Dear Virendra,
The planning method in the project profile derives from the Scheduling scenario. If you see in the same screenshot you have mentioned the scheduling scenario is 2 which is a top down approach.
If zou need to change the planning method manuallz then the scheduling scenario must be blank(which means it should be free scheduling)
Please go through SAP PS help document to understand more about the PS planning and scheduling aspects
Regards
Vittal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra,
your understanding is not correct. as we have same setting for project profile even created lots of project by that project profile but i am able to edit those.
so any other reason might be for the same
lets wait for other expert comments.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.