on 07-08-2015 10:54 AM
Hi Guru's,
I am facing one strange issue during Batch Job of TECO that system is selecting the Production Orders as per the Selection Criteria defined in the Selection Screen of COHV i.e. Plant and System Status:DLV but not doing the TECO for the Selected Production Orders.
Kindly give ur expert advice to overcome the issue.
With Regards.
Hi
Do you have any Enhancement running in Production Order level ( CO02) where PO can only be TECOed on the following condition
1.Order Balance Zero
2.No Open Reservation or open Goods Issue qty in the production order
3.All the Final Issue Indicator should be marked in Components in PO
4.No COGI error
Check whether the following any of the Badi implemented in CO02-
PPCO0002
PPCO0004
BADI -WORKORDER_UPDATE
Please check and revert
regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.