Commitment values

Hello Experts,

I am facing issue in commitment value. A matl component has been attached to an activity & a PR has been generated accordingly.

Suppose the value of it is 100,PO created, & 50% GR done against it.

Now, when  check the slr_558 report, it shows BDGT(200), ATUAL(50) , COMMITMENT(100) , ASSIGNED(150), AVAIL.(50).

I have reconstructed the DB by cjen,cjbn,rkan..,rkac..programs. etc., but still the issue persist.

The problem is even if complete complete GRN is done, then also the commitment values are seen as 100, instead of 0.

In OPSC, in ctrl indicator, Planning indicator is not ticked.

In OPSV, for 20(N/W), "appended plan update" & "Assign funds in Plan" indicators are ticked.

Kindly Suggest.

BR.