on 07-02-2015 5:29 PM
Hi Experts,
I have some doubts and need your help please.
1. In sap help it is mentioned that : from ECC to SCM
Task list usage
· Intervals
· Versions
· Hierarchies
· Definitions (shifts, break patterns, shift sequences)
Question -- I have seen new resource intervals being transferred to APO from ECC. Does it mean that if we integrate ECC and APO using External capacity indicator for resource then the above statement about the parameters not being transferred does not hold good ?
2. If I maintain capacity variants straight in APO, is there a risk that weekly CIF jobs for integration of resources will delete these capacity variants ?
3. Is there some way in ECC -- to maintain capacity variants ? I guess ---its 'version' in workcenter. If yes -- then after certail period if changes are required in version --then are those changes transferred to APO?
Rgds
Learner.
Hi,
1. With external capacity the work center in APO will use the capacity (intervals & shifts) from ECC
2. Capacity variant is specific for APO. Will not be deleted. In this case you are no working with external capacity.
3. In ECC you can't create capacity variant (is specific for APO system)
Thanks,
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Marius but its not fully clear to me.
Questions:
1. If I have in SPRO in ECC --Set the Transfer of Resources to SAP APO-->
external for all the resources then can I create capacity variants in APO or not ?
2. I understand that I can not create capacity variant in ECC but if I create version and CIF the resource -- can I acheive the same results ?
Hi Learner,
From SAP help:
1. You cannot define any intervals for resources with an external capacity that is determined directly from SAP R/3. The capacity variant is identical to the available capacity determined from the external capacity, as long as you have not manually defined variances in the capacity profile.
If you define a capacity variant as the active variant in the
General Data
of a resource, the system uses the capacity variant instead of the standard available capacity or the external capacity.
2. Nope you can't. Must be maintained in APO. You can create 99 cap.variants!
Thanks,
Regards, Marius
Hi Learner,
I agreed with you that is not very clear.
Based on SAP note 727719 you need to have an active variant defined. So, even if you have external capacity option in APO if you have an active variant the heuristic will take in consideration the capacity variant defined in APO.
From 727719:
"One of the capacity variants of a resource can be defined as an active variant and then it shows the available capacity of the resource which is relevant for planning. If no active variant is defined, the standard capacity or external capacity of the resource is used."
Thanks,
Regards, Marius