on 07-02-2015 6:32 AM
Hi Experts
I have need to extract data from r/3 system
Work center available capacity (Work center name, plant, calendar, available hours per day)
Routing (Material, plant, work center, operation, base unit, setup time and variable time)
i reach most things by using table but cant find available hr per day if i am not wrong it should be available capacity
have any solution
Thanks in advance
Thanks Experts
i have one more doubt regarding extract routing data.
I have only plant Input
I want plant- work center- material-routing data combination in one stroke.
because data is to large so need some table.
Thanks
Piyush
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Piyush,
As already stated by expert R Brahmankar use CM01 or the BAPI, but keep in mind while defining this report that capacity in work center or group work centers (depending upon how are you using) would not be individually per material. This means if 5 materials have same work center as operation in their routing's then total would 40hrs per day (example, if 8hrs and 5 capacity maintained) only and it will not split as there is no such information per material (at least planned capacity).
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Checkreport CM01 to get available capacity week wise or day wise
Input screen in the menu click on Settings-->general-->choose the radio button for day.
Else you can get the work center and capacity details through this BAPI
CR_CAPACITIES_OF_WORKCENTER.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.