Hi All,


After completion of GR I have changed Partial deliveries allowed status in the sales order header and item level and CMR.

After saving the SO schedule lines became 0...I want to do partial delivery.

Could you please help on this.

Regards,

Viswanath

Accepted Solutions (0)

Answers (1)

Answers (1)

harry_wu
Contributor
0 Kudos

In standard individual purchasing scenario:

SO item is not relevant to ATP check.

ATP check is done in delivery.

So:

- when partial GR is done,

- if you create delivery, ATP is supposed to confirm the available qty (GRed qty) only.