07-02-2015 3:34 AM
Hi SAP gurus,
I configured the PP similarly on how I used to configured standard SAP, though I'm aware that we can only run RP per site.
I am new to IS-Retail, and I'm having a problem upon running MD61.
It shows:
Message no. 6P492 -
This cause of this could be:
1. No strategy group has been maintained in the material master record.
But upon checking article master in MM43, there's no space for assigning Strategy Group unlike in standard SAP MRP3 tab.
I hope you could help me on where could I assign the strategy group to resolve this error.
Thank you in advance!
Best regards,
Kristine
07-05-2015 1:42 PM
Hi Kristine,
In article master Logistic DC tab click RP/Forecast Data icon as shown in below screen shot
Regards,
Mohan
07-06-2015 3:39 AM
Hi Sir Mohanavel,
Planning part is not visible RP/Forecast Data: DC.
Is there anything that we should activate in IS-Retail setting to have this?
Regards,
Kristine