Hello Experts,

I am trying to create PR with PS network activity but system is generating each line item has one PR.But my user requirement if you are creating multiple line items perticular activity it will come under one PR.

Through SCN i have activated OPUV collective requistion check box for control key.even though system is generation single pr for each line item.

I observed through SCN ECC 6.0 we don't have any option to create single PR for multiple line item perticular activity?

Anyone can suggest is there any possiblity to create one PR for multiple line litems with perticular network activity.

Advance thanks for your help.

Best Regards,

Srinivas.