Hi Gurus,

I am facing an issue where in we have a third party system (CMX system) from where orders are calibrated and closed. Upon on closing in CMX orders get TECHO in SAP and subsequently the date will come as completion date on the day they have closed.

Now the issue is user has manually closed the order in SAP on 05.06.2015 but the order completion date is showing as 11.06.2015. How can I chnage the date in IP10 to 11.06.2015.

Please find the attached screenshots for both in IP10 and in order. Please advice.

regard's,

Kiran.

Capture_2.JPG (24704 B)
Capture_1.JPG (49965 B)
Former Member
Former Member replied

Parvesh,

by looking at your screen shot next scheduled aclla re alraedy called then what are you trying to acheived here.

I don't thing once following Call is called system will allow you to change completion date.

Rgds

Sunil

0 View this answer in context