Hi,

I have noticed that on the standard installation of Fiori Apps Track PO and Approve PO that the display of the dates is treated differently.  In Approve PO App the date format is UK as in 'June 26 2015', but in the Track PO App it is 6/29/2015 which is US format.  Is there a setting which controls this per App or generally?

Thanks.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Darren,

I also facing the same issues. Date format is US format. In SU01, change to format 'DD.MM.YYYY', but not helpful.

Do you solve the issues? and how? Thanks.

Best regards,

Derrick

former_member185875
Contributor
0 Kudos

Hi,

In Gateway system - SU01 maintain required date format.

Hope it will work.

If not, For better understanding upload your application screenshots.


Thanks,

Lakshman Balanagu.

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Lakshman,

Please check the metadata data type and the OData response from backend.

The first step is that finding the issue is in the frontend side or the backend side.

Regards,

Masa / SAP Technology RIG

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Darren,

Could you upload the screenshots?

Please share the support package level for the apps.

Regards,

Masa / SAP Technology RIG

Darren2
Explorer
0 Kudos

Hi Masa,

Support package details are: UIX01EAP Release 100 SP 4, SRA020 Release 600 SP 6.

Regards,

Darren

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Darren,

Please look at the required support package level.

App Implementation: Track Purchase Order - SAP Fiori Apps - SAP Library

Regards,

Masa / SAP Technology RIG

Darren2
Explorer
0 Kudos

Hi Masa,

We have another system patched to the higher level SP7 and this acts in exactly the same way.

Any further thoughts?

Regards,

Darren.

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Darren,

Could you upload a screenshot for the Approve PO?

Regards,

Masa / SAP Technology RIG

Darren2
Explorer
0 Kudos

Hi Masa,

Please see approve PO below, which is using the same user as for the Track PO.

Thanks,

Darren.

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Darren,

What is the browser language setting? Is it en-US or en-GB or something else?

Regards,

Masa / SAP Technology RIG

Darren2
Explorer
0 Kudos

Hi Masa,

Yes, it's set as EN with UK reference to the formatting for numbers and dates.

Regards,

Darren.

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Darren,

Are those screenshots with UIX01EAP SP06?

I think Approve PO should show today or X days ago. I guess support package for UI is not SP06.

Please double check it again.

Regards,

Masa / SAP Technology RIG

Darren2
Explorer
0 Kudos

Hi Masa,

The support package on our other system is SP06 and has exactly the same issue with date formatting.

Regards,

Darren.

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Darren,

Please share the date format setting in SU01.

Logon user in ERP:           DD.MM.YYYY

Logon user in Gateway:    DD.MM.YYYY

WF-BATCH user in ERP:  DD.MM.YYYY

Regards,

Masa / SAP Technology RIG

Darren2
Explorer
0 Kudos

Hi Masa,

Yes, they are all set to DD.MM.YYYY.

Regards,

Darren.